Led by Senior Process Plant Engineer Simulacrum
Process plant shutdown and start-up from turnaround planning and critical path scheduling through isolation, execution, risk management, PSSR, commissioning, post-start-up monitoring, troubleshooting, and turnaround optimisation.
Led by Senior Process Plant Engineer Simulacrum
The question
A turnaround is won or lost in the planning — and a turnaround that runs one day over costs the full daily production revenue in lost output. This module covers the turnaround lifecycle from initiation to closeout, scope development from the four sources (inspection, maintenance backlog, reliability improvement, MOC), critical path scheduling (the longest chain of dependent activities that determines the minimum duration), resource levelling to avoid unworkable labour peaks, long-lead material procurement, and the turnaround organisation chart with its defined authority structure.
Outcome
The student can describe the turnaround lifecycle, explain critical path scheduling, describe the scope development process, and explain the resource levelling concept. (Shutdown planning and scheduling)
Sub-units
Led by Senior HSE Engineer Simulacrum
The question
The shutdown sequence takes the plant from normal operation to a safe, de-energised state through a controlled series of steps — each with a precondition that must be verified. This module covers the seven-step shutdown sequence from rate reduction to confirmed isolation, the four isolation methods (single-block, double-block-and-bleed, spade/blind, electrical LOTO) and when each is appropriate, the isolation certificate with its independent verification requirement, critical path execution and duration tracking, vessel and piping inspection during shutdown, and waste management during the turnaround.
Outcome
The student can trace the shutdown sequence, describe all four isolation methods and their risk levels, describe the isolation certificate requirements, and identify four typical critical-path work packages. (Shutdown execution)
Sub-units
Led by Senior HSE Engineer Simulacrum
The question
A turnaround concentrates more hazards into a shorter time than any other operational period — hundreds of unfamiliar contractors, open equipment, simultaneous activities, and the transition between shutdown and start-up states. This module covers the turnaround-specific HAZOP, the task risk assessment performed before each work package, the SIMOPS matrix and its three conflict categories (prohibited, restricted, unrestricted), permit-to-work volume management during a turnaround, the daily coordination meeting, radio protocol and escalation procedures, and contractor safety management (induction, competency, supervision ratios).
Outcome
The student can describe the turnaround HAZOP and TRA, explain the SIMOPS matrix with examples, describe the PTW volume management controls, and explain the contractor induction and supervision requirements. (Risk management and communication during shutdown)
Sub-units
Led by Senior Instrumentation & Control Engineer Simulacrum
The question
The start-up after a turnaround is the highest-risk period — equipment that was opened and repaired may leak, instruments may be miscalibrated, and the first introduction of hydrocarbon is the point of no return. This module covers the PSSR (the seven verification items and the three-signature authorisation), the eight-step start-up sequence from pressure testing through hydrocarbon introduction to design capacity, commissioning of new equipment (loop testing, functional testing, performance testing), post-start-up monitoring during the critical first 72 hours, and turnaround closeout documentation.
Outcome
The student can describe the PSSR and its regulatory basis, trace the start-up sequence, explain the three commissioning test types, and describe the post-start-up monitoring programme. (Start-up, commissioning, and testing)
Sub-units
Led by Senior Process Troubleshooter Simulacrum
The question
Things go wrong during every turnaround. Equipment is found in worse condition than expected. A new installation does not perform. A leak is discovered during start-up. This module develops the troubleshooting discipline for shutdown (unexpected corrosion, scope changes, critical path impact) and start-up (process loop errors, instrument failures, leaks after hydrocarbon introduction), the start-up-specific safety framework, turnaround optimisation techniques for duration (pre-fabrication, modularisation), cost (standardisation, scope challenge), and safety (permanent isolation valves), and three case studies from major turnaround incidents.
Outcome
The student can diagnose and respond to three turnaround scenarios, describe the start-up safety controls, and describe three optimisation techniques each for duration, cost, and safety. (Troubleshooting, safety, and optimisation)
Sub-units