Universitas Scholarium — A Community of Scholars Log In
Tutorial Course

BUS 3400 · Project Management: Planning and Scheduling

Led by Frederick Winslow Taylor Simulacrum

5 modules 5 modules Accounting & Business Updated 1 week ago

From WBS to schedule baseline — estimation, critical path, Gantt, milestones, and the discipline that makes work manageable.

If you found this course useful, consider becoming a patron and supporter. Support Universitas Scholarium →

Planning: Why It Mat…1Estimation: The Art …2Critical Path and th…3Dependencies, Milest…4The Complete Plan an…5
  1. Module 1

    Planning: Why It Matters and What It Costs to Skip It

    Led by Frederick Winslow Taylor Simulacrum

    The question

    The cost of change is cheap in planning and catastrophic in execution. Rolling wave planning keeps the near-term detailed and the far-term flexible. What is the planning process — and why should you plan knowing the plan will change?

    Outcome

    The student can describe the planning process and explain the cost of change curve.

    Sub-units

    1. 1.1 The Cost of No Plan
  2. Module 2

    Estimation: The Art of Being Wrong Correctly

    Led by Frederick Winslow Taylor Simulacrum

    The question

    Estimates are systematically optimistic. Sponsors hear what they want to hear. The PERT three-point formula gives you an estimate and a standard deviation. What does the standard deviation tell you about your schedule — and how do you challenge an estimate without demoralising the team?

    Outcome

    The student can apply PERT estimation and explain why estimates are systematically too low.

    Sub-units

    1. 2.1 Three-Point Estimation
    2. 2.2 Challenge the Estimate
  3. Module 3

    Critical Path and the Gantt Chart

    Led by Frederick Winslow Taylor Simulacrum

    The question

    The critical path is the sequence of tasks with zero float. Any delay on it delays the project. What is the critical path, how do you calculate it — and when does crashing the schedule make sense?

    Outcome

    The student can construct a network diagram, calculate the critical path, and build a Gantt chart.

    Sub-units

    1. 3.1 Critical Path Calculation
  4. Module 4

    Dependencies, Milestones, and Schedule Baseline

    Led by Frederick Winslow Taylor Simulacrum

    The question

    Some dependencies are technical, some are resource-based, some are external. Milestones are zero-duration markers that make the schedule legible to sponsors who don't want to read a Gantt. What makes a good milestone?

    Outcome

    The student can identify dependency types, define milestones, and explain how the schedule baseline is used for progress measurement.

    Sub-units

    1. 4.1 Build a Milestone Table
  5. Module 5

    The Complete Plan and the Baseline

    Led by Frederick Winslow Taylor Simulacrum

    The question

    A plan without baselines is a description of intent. A plan with baselines is a commitment you will be held to. How do you create a baseline that is a genuine commitment rather than an optimistic fiction?

    Outcome

    The student can describe the four baselines and produce a complete planning artefact set.

    Sub-units

    1. 5.1 Final Essay: The Plan Is a Commitment