Led by Frederick Winslow Taylor Simulacrum
From WBS to schedule baseline — estimation, critical path, Gantt, milestones, and the discipline that makes work manageable.
If you found this course useful, consider becoming a patron and supporter. Support Universitas Scholarium →
Led by Frederick Winslow Taylor Simulacrum
The question
The cost of change is cheap in planning and catastrophic in execution. Rolling wave planning keeps the near-term detailed and the far-term flexible. What is the planning process — and why should you plan knowing the plan will change?
Outcome
The student can describe the planning process and explain the cost of change curve.
Sub-units
Led by Frederick Winslow Taylor Simulacrum
The question
Estimates are systematically optimistic. Sponsors hear what they want to hear. The PERT three-point formula gives you an estimate and a standard deviation. What does the standard deviation tell you about your schedule — and how do you challenge an estimate without demoralising the team?
Outcome
The student can apply PERT estimation and explain why estimates are systematically too low.
Sub-units
Led by Frederick Winslow Taylor Simulacrum
The question
The critical path is the sequence of tasks with zero float. Any delay on it delays the project. What is the critical path, how do you calculate it — and when does crashing the schedule make sense?
Outcome
The student can construct a network diagram, calculate the critical path, and build a Gantt chart.
Sub-units
Led by Frederick Winslow Taylor Simulacrum
The question
Some dependencies are technical, some are resource-based, some are external. Milestones are zero-duration markers that make the schedule legible to sponsors who don't want to read a Gantt. What makes a good milestone?
Outcome
The student can identify dependency types, define milestones, and explain how the schedule baseline is used for progress measurement.
Sub-units
Led by Frederick Winslow Taylor Simulacrum
The question
A plan without baselines is a description of intent. A plan with baselines is a commitment you will be held to. How do you create a baseline that is a genuine commitment rather than an optimistic fiction?
Outcome
The student can describe the four baselines and produce a complete planning artefact set.
Sub-units